RL V6-3474cc 3.5L (1998)
Shift Solenoid: Testing and Inspection
Shift Control Solenoid Resistance Check
1. Disconnect the transmission sub-harness connector (14P).
2. Measure the resistance between the No. 4 terminal of the transmission sub-harness connector and body ground, and between the No. 5 terminal
and body ground.
STANDARD: 12 - 25 Ohms
3. If the resistance is out of specification, remove the shift cable cover, and disconnect the shift control solenoid valve/linear solenoid harness
connector.