The following work sequence is recommended to save time when the crown wheel and pinion shaft have to be adjusted: |
t
| Determine total shim thickness „Stotal“ (S3 plus S4) for the specified preload on pinion shaft tapered roller bearings. |
t
| Distribute total shim thickness „Stotal“ (S3 plus S4) so that distance from centre of crown wheel to end face of pinion shaft corresponds to installation dimension „R“ determined during production. |
t
| Determine total shim thickness „Stotal“ (S1 plus S2) to obtain specified preload on differential tapered roller bearings. |
t
| Distribute total shim thickness „Stotal“ (S1 plus S2) so that the specified backlash between crown wheel and pinion shaft is obtained. |
|
|
|