Installing
Install in reverse order, paying attention to the following:
Note:
Always replace gaskets and sealing rings.
-
‒ Clean/smooth sealing surface for O-ring.
-
‒ → Fit thermostat -4- with new O-ring -3- in connection -2- and turn a quarter turn (90 °) clockwise.
Note:
The bar on the thermostat must be pointing virtually straight up.
-
‒ Fit connection with thermostat into cylinder block.
-
‒ Tighten bolts -1-.
-
‒ Fill cooling system with coolant => Page 19-11.
Tightening torque
|
---|
Component
|
|
Nm
|
Thermostat connection to cylinder block
|
13
|
Checking thermostat
-
‒ Heat thermostat in water bath.
|
---|
Start of opening
|
End of opening
|
Opening stroke
|
approx. 87°C
|
approx. 102°C 1)
|
min. 8 mm
|
1) Not testable
|