‒ → Connect one of the contacts on the solenoid valve to engine earth using test leads and crocodile clamp from V.A.G 1594 A.
-
‒ Connect second contact on -N156 to positive using remote control V.A.G 1348/3A, adapter lead V.A.G 1348/3-2 and auxiliary cable.
-
‒ Operate remote control V.A.G 1348/3A approx. 2 to 3 minutes; throughout this period, the vacuum unit should pick up.
If the vacuum unit returns to its original "rest" position, carry out the following test:
-
‒ Disconnect vacuum hoses from vacuum unit for intake manifold changeover system.
-
‒ Connect hand pump V.A.G 1390 to vacuum unit.
-
‒ Operate hand pump and check whether changeover function is working.
-
‒ Check vacuum unit for leaks. (The vacuum unit should not return to rest position until the hand pump is vented to atmosphere.)
-
‒ If necessary, renew vacuum unit.
-
‒ If the vacuum unit does not pick up, check -N156 as follows for blockage:
|