Procedure before opening high-pressure section of injection system
Procedure before opening high-pressure section of injection system
t  The injection system consists of a high-pressure section (maximum approx. 120 bar) and a low-pressure section (approx. 6 bar).
t  The fuel pressure in the high-pressure section must be reduced to a residual pressure of approx. 6 bar prior to opening the system. The procedure is described below.
Special tools and workshop equipment required
t  Vehicle diagnostic, testing and information system -VAS 5051B-
   
Procedure
Proceed as follows:
–  With ignition switched off, connect vehicle diagnostic, testing and information system -VAS 5051B-.
  A01-0201
Display on -VAS 5051B-:
–  Select Vehicle self-diagnosis from the list -item 1-.
  A01-10029
Display on -VAS 5051B-:
–  From menu -1-, select vehicle system “01 - Engine electronics” and press key to continue.
  A01-10008
Display on -VAS 5051B-:
–  From menu -1-, select diagnosis function “006 - Basic setting” and press key to continue.
  A01-10024
Display on -VAS 5051B-:
–  Press keys 140 on keypad -1- to select “Display group 140” and confirm entry by pressing Q key.
  A01-10026
Display on -VAS 5051B-:
Example
1 - 42 %
2 - 39.76 bar
3 - 40.63 bar
4 - inactive
  A01-10027
–  Activate basic setting by touching key A.
Display on -VAS 5051B-:
Example
1 - 0 %
2 - 0 bar
3 - 5.46 bar
4 - reduce
The fuel rail is still filled with fuel, however it is no longer under high pressure.
Components or lines can now be opened.
–  Wrap a clean cloth around the connections and catch escaping fuel.
Additional steps required
–  Start “Guided Functions” mode.
–  Generate readiness code in engine control unit.
  A01-0163

General repair instructions > < Safety precautions