audi Workshop Repair Guides

Audi Workshop Service and Repair Manuals

Fuel Metering Valve, Checking|Page 3628 > < Fuel Metering Valve, Checking|Page 3626
Page 3
background image

If no malfunctions are found in the wiring:

Checking wiring connections

If the manufacturers test box is being used, perform the following step.

-

Install the test box. Refer to appropriate repair information.

If the manufacturers test box is not being used, perform the following step.

-

Remove the Engine Control Module (ECM) (J623). Refer to appropriate repair information

-

Using a multimeter, check the Fuel Metering Valve (N290) electrical harness connector terminal 2 to the Engine Control Module (ECM) (J623)
electrical harness connector T60 terminal 19 for an open circuit.

Specified value: 1.5 ohms Max.

If the specification was not obtained:

-

Check the wiring for a short circuit to each other, Battery (+), and Ground (GND), or an open circuit.

-

If necessary, repair the faulty wiring connection.

If no malfunction is detected in the wiring:

-

Replace the Engine Control Module (ECM) (J623). Refer to appropriate repair information.

-

Assembly is performed in the reverse order of removal.

Final procedures

After the repair work, the following work steps must be performed in the following sequence:

1. Check the DTC memory. Refer to => [ Diagnostic Mode 03 - Read DTC Memory ] See: Computers and Control Systems/Testing and

Inspection/Scan Tool Testing and Procedures/Diagnostic Modes 01 - 0A. 

2. If necessary, erase the DTC memory. Refer to => [ Diagnostic Mode 04 - Erase DTC Memory ] See: Computers and Control Systems/Testing and

Inspection/Scan Tool Testing and Procedures/Diagnostic Modes 01 - 0A.

3. If the DTC memory was erased, generate readiness code. Refer to => [ Readiness Code ] See: Computers and Control Systems/Testing and

Inspection/Monitors, Trips, Drive Cycles and Readiness Codes.

Fuel Metering Valve, Checking|Page 3628 > < Fuel Metering Valve, Checking|Page 3626