9. Install the cooler line into the quick connect fitting. 

10. Insert the cooler line end into the quick connect fitting until a click is either heard or felt. 

11. Do not use the plastic cap on the cooler line in order to install the cooler line into the fitting. 
12. Pull back sharply on the cooler line in order to ensure that the cooler line is fastened into the quick connect fitting. 

13. Position (snap) the plastic cap onto the fitting. Do not manually depress the retaining ring when installing the plastic cap onto the quick connect

fitting. 

14. Ensure that the plastic cap is fully seated against the fitting. 