1. Disconnect wire harness (1) from the stud as shown in illustration.
2. Remove coolant surge tank fastener (2) and set coolant surge tank to the passenger side of engine compartment as shown in illustration.
3. Clean generator in the 2 o'clock area with a shop towel.
4. Use a pencil to shade the generator build date code.

-

If the generator build date is January 5, 2010 or later, remove the generator and replace it with a new one. Proceed to step 2.

-

If the generator build date is BEFORE January 5, 2010, replacement of the generator is NOT required. No further action is required.

2. Remove the generator and auxiliary generator, if required, from the vehicle. Refer to Generator Replacement and/or Auxiliary Generator

Replacement in SI.

Note
Gasoline Engine ONLY - DO NOT connect the negative battery cable UNTIL steps 4-6 have been completed.

3. Install the new generator. Refer to Generator Replacement and/or Auxiliary Generator Replacement in SI.

-

If the vehicle is equipped with a gasoline engine, proceed to step 4.

-

If the vehicle is equipped with a diesel engine, no further action is required.

4. Route engine harness generator inline below the main branch of engine harness.