1987 through 1989 2.5L truck engines - The set screw, as shown in Figure 2, needs to be removed form the new partial engine assembly. Apply
Loctite (R) 242 or equivalent to the set screw and reinsert into the the block. The set screw should be seated flush to the boss surface. This step is
required for two reasons:

A.

The set screw is loosely threaded into the partial engine block as shipped from GMSPO and

B.

The threaded hole breaks out into the coolant jacket and requires application of a sealant to the set screw to prevent a coolant leak.

This step must also precede installation of the air conditioning compressor support, as shown in Figure 2, if so equipped.