Sebring V6-2.5L SOHC 24 Valve (1996)
Valve Body: Testing and Inspection
LR Solenoid Check
LR SOLENOID CHECK
1. Disconnect the solenoid & pressure switch assembly connector.
2. Measure the resistance between the solenoid & pressure switch assembly side connector terminals 4 and 6.
-
Standard value: Approx. 1 ohm [at 20°C(68°F)].
3. If the resistance is outside the standard value, replace the solenoid & pressure switch assembly.
2/4 Solenoid Check
2/4 SOLENOID CHECK
1. Disconnect the solenoid & pressure switch assembly connector.
2. Measure the resistance between the solenoid & pressure switch assembly side connector terminals 3 and 6.
-
Standard value: Approx. 1 ohm [at 20°C(68°F)].
3. If the resistance is outside the standard value, replace the solenoid & pressure switch assembly.
OD Solenoid Check
OD SOLENOID CHECK
1. Disconnect the solenoid & pressure switch assembly connection
2. Measure the resistance between the solenoid & pressure switch assembly side connector terminals 6 and 8.
-
Standard value: Approx. 1 ohm [at 20°C(68°F)].
3. If the resistance is outside the standard value, replace the solenoid & pressure switch assembly.