10. Discard the retaining ring.

11. Pull the cooler line straight out from the quick connect fitting.
12. Remove the retaining ring (E-clips) securing the cooler line to the quick connect in order to remove the remaining cooler lines from the remaining

quick connect fittings.

13. Remove the cooler lines from the vehicle.
14. Lower the vehicle.

Installation Procedure

1. Raise the vehicle.

2. Install the transmission oil cooler line to the vehicle.

3. Important:  Do not reuse any of the existing retaining rings that were removed from the existing quick connect fittings. All retaining rings being

installed must be New.

Install the new retaining ring (E-clip) into the quick connect fitting.

4. Install the 2 cooler lines to the radiator.