QX56 AWD V8-5.6L (VK56DE) (2005)
^
The sections must be performed in order 1 through 5.
Section 1:
Connect a battery charger and CONSULT-II to the vehicle.
Section 2:
Check all systems in "SELF-DIAG" RESULTS and erase any DTC(s).
Section 3:
Confirm the vehicle battery voltage and CONSULT-II Charger Input.
Section 4:
Perform ABS/VDC Control Unit Reprogramming.
Section 5:
Again perform a check of all systems in "SELF-DIAG" RESULTS and erase any newly stored DTC(s).
Section 1
Section 1: Connect a battery charger and CONSULT-II to the vehicle.
1.
Confirm the ignition switch is OFF.
2.
Connect a battery charger to the vehicle battery.
Set the charger at a low charge rate (2-amp "trickle charge").
IMPORTANT
You must connect a battery charger to the vehicle battery when performing ABS/VDC reprogramming. Permanent ABS/VDC damage can occur if
you don't.
Connecting a vehicle battery charger will maintain:
^
Proper CONSULT-II power supply during reprogramming-very important if the CONSULT-II battery is low.
^
Vehicle battery voltage level-especially on late model vehicles where the cooling fans come on during reprogramming.
3.
Connect CONSULT-II to the vehicle using the DLC-II cable with black Converter Box (see Figure 11).
VERY IMPORTANT:
^
Make sure the DLC-II is pushed in straight and fully plugged in to the vehicle connector.
^
Make sure all other DLC-II cable connections (as shown in Figure 11) are connected properly.
CAUTION
^
Infiniti requires the use of essential tools shown in Figure 11 when performing ABS/VDC reprogramming
^
J44200-10 "Pigtail" should not be removed from the CONSULT-II DDL Port. This "Pigtail" allows use of the stronger "quick disconnect" cable
set.