X-Type (X400) V6-3.0L (2002)
30.
Install a suitable dial test indicator to the steering gear dial gauge with an extension to the needle through special tool (211-329-05) directly onto
the back of the pretensioner pad (Illustration 20).
Note:
Should the clearance not be correct, the pre-load adjusting nut must be moved by a single division at a time to achieve the correct clearance.
31.
Using care so that the steering gear body does not move during the operation, check the pre-load by lifting the rack bar by hand. The clearance
must be minimum 0.05mm and maximum 0.1 mm (Illustration 21).