XJ (X350) V8-4.2L (2005)
4.
*Mark and drill two 5 mm (0.200 in) holes on both sides of the left-hand crush tube. (Figure 3)*.
5.
*Apply Loctite(R) Threadlocker Blue to each new screw*.
6.
*Tighten each screw to 12 Nm (8.85 lbf-ft)*.
7.
*Drill two 5 mm (0.200 in) holes on both sides of the right-hand crush tube. (Figure 4)*.
8.
*Apply Loctite(R) Threadlocker Blue to each new screw*.
9.
*Tighten each screw to 12 Nm (8.85 lbf-ft)*.
10.
*Install the A/C pipe foam block support to the chassis frame. (Figure 2)*.
11.
*Install the sight shield moldings and radiator air deflectors. (Figure 1)*.
*NOTE:
Global Technical Reference (GTR) lockup sequence is as follows: