jeep Workshop Repair Guides

Jeep Workshop Service and Repair Manuals

Valve Spring > < Valve Cover|Removal|Page 1957
Page 2
background image

NOTE: When using RTV, parts should be assembled in 10 minutes and tighten to final torque within 45 minutes.

4.   Apply a dot of Mopar(R) engine sealant RTV or equivalent to cylinder head/front cover T-joint (1).

5.   Install cylinder head cover assembly to cylinder head and install all bolts, ensuring the studs are located as shown. 
6.   Tighten bolts in sequence shown using a 2 step torque method as follows:

a.   Tighten all bolts to 5 Nm (44 in. lbs.)
b.   Tighten all bolts to 10 Nm (90 in. lbs.).

7.   Install ignition coils. Tighten fasteners to 8 Nm (70 in. lbs.).
8.   If the PCV valve was removed, tighten PCV valve to 5 Nm (44 in. lbs.).
9.   Connect PCV and make-up air hoses to cylinder head cover.

10.   Install engine cover.

Valve Spring > < Valve Cover|Removal|Page 1957