GS 300 L6-3.0L (2JZ-GE) (1993)
Variable Induction Control Valve: Service and Repair
Installation
PROCEDURE
1. Install Vacuum Tank and Vacuum Switching Valve with the screw to the vacuum tank. Install the vacuum hose.
2. Install vacuuum control valve set with the 2 nuts.
Torque: 21 Nm (15 ft lb)
Connect the connector to the Vacuum Switching Valve.
3. Install air intake chamber.
-
Place the gasket so the protrusion faces the intake chamber.
-
Install a new gasket to the intake manifold, and install the intake chamber with the 5 bolts and 1 nut.
Torque: 21 Nm (15 ft lb)
-
Install the 2 nuts holding the Throttle Body bracket to the cylinder head.
Torque: 18 Nm (13 ft lb)
-
Install the 4 bolts and 2 nuts holding the intake air connector to the air intake chamber.
Torque: 18 Nm (13 ft lb)
-
Install the 2 bolts holding the chamber stays to the air intake chamber.
Torque: 18 Nm (13 ft lb)