Power Window Switch: Component Tests and General Diagnostics

Power Window Main Switch Inspection

POWER WINDOW MAIN SWITCH INSPECTION

1. Switch the ignition to ON.

2. Verify that the door glass (driver's side) can be operated for approx. 43 s after the ignition is switched off. 

-

If the door glass (driver's side) cannot be operated for approx. 43 s after the ignition is switched off, or if the door glass (driver's side) can still
be operated after approx. 43 s, replace the power window main switch.

3. Disconnect the negative battery cable.

4. Remove the inner garnish. (driver's side) See: Body and Frame/Doors, Hood and Trunk/Doors/Front Door/Front Door Panel/Service and

Repair/Removal and Replacement/Inner Garnish Removal/Installation

5. Remove the front door trim. (driver's side)  See: Body and Frame/Doors, Hood and Trunk/Doors/Front Door/Front Door Panel/Service and

Repair/Removal and Replacement/Front Door Trim Removal/Installation

6. Remove the main switch panel. (driver's side) See: Body and Frame/Doors, Hood and Trunk/Doors/Front Door/Front Door Panel/Service and

Repair/Overhaul

7. Connect the power window main switch connector.

8. Connect the negative battery cable.

9. Measure the voltage at each terminal. 

-

If the voltage is not as specified in the terminal voltage table, inspect the parts under Inspection item (s) and related wiring harnesses.

10. If the system does not work normally even though the inspection items or related wiring harnesses do not have any malfunction, replace the power

window main switch.

Terminal Voltage Table (Reference)

Component Tests and General Diagnostics|Page 9085 > < Component Locations|Page 9082