Millenia L V6-2.5L DOHC (1997)
Shift Solenoid: Component Tests and General Diagnostics
INSPECTION OF RESISTANCE
1. Disconnect the negative battery cable.
2. Remove the air cleaner assembly.
3. Disconnect the solenoid valve connector.
4. Measure the resistance between terminals A through G and a ground.
5. If not correct, check the wiring harness or replace the solenoid valve(s), if necessary.
6. Connect the solenoid valve connector.
7. Install the air cleaner assembly.
8. Connect the negative battery cable.
INSPECTION OF OUTPUT DUTY FOR THE PRESSURE CONTROL SOLENOID
1. Connect the (+) terminal of a dwell meter to terminal 2H at the powertrain control module and the (-) terminal to a ground. Set the dwell meter
selector to the 4 cylinder position.
2. Engage the parking brake and use wheel chocks at the front and rear of the wheels.
3. Start the engine.
4. Depress the brake pedal firmly.
5. Shift the selector lever to D range.
NOTE: The dwell meter indicates the OFF duty ratio.