Planetary Carrier Component (1) 
Measure the clearance between the pinion washer and the planetary pinion carrier all around the edge. Standard clearance is 0.2 - 0.7 mm
(0.008 - 0.028 inch)
 and a maximum of 0.8 mm (0.031 inch).

Ring Gear (7) 
Measure the inner diameter of the bushing. Measure three times and average the results. Inner diameter standard is 54.021 - 54.055 mm
(2.1268 - 2.1281 inch)
 and a maximum of 54.100 mm (2.1299 inch).

Rear Output Shaft (9) 
1. Measure the outer diameter of the output shaft at the points shown. Measure each point three times and average the results.
2. If not within the specification, replace the output shaft.

3. Measure the output shaft runout.
4. If not within 0.030 mm (0.0012 inch) maximum, replace the output shaft.