Variable Induction Control Solenoid: Testing and Inspection
Variable Tumble Control System (VTCS) Solenoid Valve

VARIABLE TUMBLE CONTROL SYSTEM (VTCS) SOLENOID VALVE INSPECTION

Simulation Test

1. Carry out the "VTCS Operation Inspection". 

-

If not as specified, perform the further inspection for the VTCS solenoid valve.

Airflow Inspection

NOTE:  Perform the following test only as directed.

1. Remove the VTCS solenoid valve.

2. Inspect for the air flow inspection each port under the following condition.

-

If as specified, replace the VTCS solenoid valve.

-

If as specified but the "VTCS Operation Inspection" is failed, inspect evaporative hoses for improper routing, kinks or leakage, and inspect
"Circuit Open/Short Inspection".
-

If there is an open or short circuit, repair or replace wiring harnesses.

-

If the above open or short circuit is okay, replace VTCS solenoid valve.

Circuit Open/Short Inspection

1. Disconnect the PCM connector.

2. Connect the SST (104 Pin Breakout Box) to the PCM as shown.
3. Tighten the connector attaching screw.

Tightening torque
7.9 - 10.7 N.m {80 - 110 kgf.cm, 69.5 - 95.4 in.lbf}