Protege ES L4-2.0L DOHC (2001)
Shift Solenoid: Component Tests and General Diagnostics
On-Vehicle
Inspection of Resistance
1. Measure the resistances between the following terminals.
^
If any resistances are out of specifications, inspect the ground, then perform the operation and the part inspection.
Inspection of Operation
Note:
-
When inspecting the pressure control solenoid, connect the GND connection to the GND terminal (I terminal) of the pressure control solenoid
inside the solenoid valve connector.
-
Do not apply voltage for more than 3 seconds.
1. Apply B+ to terminal A, B, C, F, or G and battery negative voltage to GND, and verify that a click sound is heard from each solenoid.
^
If the click sound is not heard from each solenoid, replace solenoids.
2. Apply B+ to terminal D and battery negative voltage to terminal I, and verify that a click sound is heard from solenoid.
^
If the "click" is not heard, replace the solenoid valve.
Off-Vehicle
Resistance Inspection (Off-vehicle)
1. Measure the resistance of each solenoid valve individually.