Protege LX L4-1.6L DOHC (2000)
Circuit Open/Short Inspection
1. Remove the PCM.
2. Connect the SST (104 Pin Breakout Box) to the PCM as shown.
3. Tighten the connector attaching screw.
Tightening torque:
7.9 - 10.7 N.m {80 - 110 kgf.cm, 69.5 - 95.4 in.lbf}
4. Inspect for an open or short circuit in the following wiring harnesses by probing the applicable sensor and SST (104 Pin Breakout Box) terminals
with ohmmeter leads.
-
If there is an open or short circuit, repair or replace wiring harnesses.
-
If there is no open or short circuit, replace the fuel tank pressure sensor.
Open circuit
-
Fuel tank pressure signal circuit (Fuel tank pressure sensor connector terminal B and PCM connector terminal 62)
-
Reference voltage circuit (Fuel tank pressure sensor connector terminal C and PCM connector terminal 90)
-
GND circuit (Fuel tank pressure sensor connector terminal A and PCM connector terminal 91)
Short circuit
-
Fuel tank pressure signal circuit (Fuel tank pressure sensor connector terminal B and PCM connector terminal 62)
-
Reference voltage circuit (Fuel tank pressure sensor connector terminal C and PCM connector terminal 90)
5. Reconnect the fuel tank pressure sensor connector.