Main Relay (Computer/Fuel System): Testing and Inspection
Component Inspection

NOTE:  Perform the following test only when directed.

1. Disconnect the negative battery cable.

2. Remove the main relay.

3. Inspect for continuity between terminals of the relay using an ohmmeter.

-

If not as specified, replace the main relay.

-

If the main relay is okay, but PCM terminal 71 or 97 voltage is out of specification, carry out the "Circuit Open/Short Inspection".

Circuit Open/Short Inspection

1. Remove the PCM.

2. Connect the SST (104 Pin Breakout Box) to the PCM as shown.
3. Tighten the connector attaching screw.

Tightening torque:
7.9 - 10.7 N.m {80 - 110 kgf.cm , 69.5 - 95.4 in.lbf}