mercedesbenz Workshop Repair Guides

Mercedes Benz Workshop Service and Repair Manuals

Engine Block Heater - Installation/Cable Installation|Page 1703 > < Engine Block Heater - Installation/Cable Installation|Page 1701
Page 3
background image

12.

The cable may now be easily accessed for winter use or alternately reinserted through the slot in the towing eye flap for storage when not needed
(Figure 6).

13.

Close coolant drain plug.

Tightening torque: 30 N-m

14.

Reinstall encapsulation panels.

15.

Test coolant for sufficient antifreeze protection, refill and bleed cooling system. Pressure test system for leaks.

16.

Run engine. Check for proper coolant level.

Parts Information

Recommended Labor Time

Operation: Block heater and electrical cable, subsequent installation

Operation Number

Time

Model

20-5480

1.4 hrs.

A1

Note:

The subsequent installation of a block heater in this model is at the customer's expense.

Additional time for "Engine compartment panel(s) - bottom. R & R" (see Time Guide microfiche, group no. 61) may be applied, provided it is not
already included in another repair or maintenance service with the same repair date.

B. Install. of Engine Block Heater 140.042/051 (400SE/500SEL)

1.

Lift vehicle and remove left front wheel.

2.

Remove front and rear encapsulation panel from below engine.

3.

Drain engine coolant at drain plug on left side of engine block. Drain coolant into a suitable container for reuse later.

4.

Remove poly-V-belt from compressor pulley. Remove A/C compressor mounting screws and move compressor forward. without disconnecting
compressor hoses.

Engine Block Heater - Installation/Cable Installation|Page 1703 > < Engine Block Heater - Installation/Cable Installation|Page 1701