Pathfinder 4WD V6-4.0L (VQ40DE) (2006)
6. Install two bolts in front of oil pan (upper) in numerical order as shown.
Front oil pan bolts : 22.0 N-m (2.2kg-m, 16 ft-lb)
7. Install right and left intake valve timing control covers as follows:
a. Install new seal rings in shaft grooves.
b. Apply a continuous bead of liquid gasket using Tool to intake valve timing control covers as shown.
Use Genuine RTV Silicone Sealant or equivalent.
Tool number : WS39930000
c. Install new collared O-rings in front timing chain case oil hole (left and right sides).
d. Being careful not to move seal ring from the installation groove, align dowel pins on front timing chain case with the holes to install intake valve
timing control covers.
e. Tighten bolts in numerical order as shown.
8. Install crankshaft pulley as follows: