1. Make sure the lead being tested is not carrying a current (e.g. by removing the associated fuse) and that any load has been disengaged.
2. Set the multimeter to resistance measurement.
3. Connect one test cable to a good ground and the other to the point to be tested.
4. Carefully move the wiring harness and make sure the multimeter shows infinite resistance (OL) the whole time.

Connectors, Handling and Inspection

Connectors, Handling And Inspection

Handling

1. When unplugging a connector that has a catch, the catch must be undone first before parting the connector. Make sure the connector catch engages