| Attach the lifting tackle -VAS 2024A- as described in the following, and remove the engine from the retention tool -T20205- using the workshop crane. |
Pulley side: 1. Borehole on the support bar in position 1 |
Flywheel side: 4. Borehole on the support bar in position 8 |
WARNING Use safety pins on the hooks and bolts. |
|
Note t
| To align the assembly centre bring the lifting tackle -2024A- to the anchorage points as shown in the figure. |
t
| The positions numbered 1 – 4 of the hoisting bar face the pulley. |
t
| The holes in the perforated flanges are counted starting from the hook. |
|
|
|