OPERATION CHECK
Whenever shift solenoid valves and TCC (lock-up) solenoid valve are removed from transmission, verify their valve function physically before they
are reinstalled.
1) Apply oiler to solenoid valve and give compression by hands and then check to be sure that transmission fluid from oiler does not come out of
holes in solenoid valve when battery voltage is not conducted.
2) Under the same conditions as above, conduct battery voltage and then make sure that fluid comes out with vigor.
NOTE:
-
If fluid does not come out with vigor in above step 2 inspection, do not re-use that solenoid valve.
-
Figure at the left shows shift solenoid valve check. Check TCC solenoid valve also in the same way.
INSTALLATION
Reverse removal procedure to install solenoid valves and nothing following points.
-
For details of solenoid valve installation, refer to "Unit Repair". Use new gasket and 0-ring.
-
Install oil tubes in such order as shown in figure.
-
For details of oil pan installation, refer to "Unit Repair".
Use new oil pan gasket.
-
Tighten oil cooler pipe flare nut, universal joint flange bolts & nuts and exhaust pipe bracket bolts to specified torque.
-
Fill A/T fluid and check fluid level according to procedure described in "CHANGING FLUID".
-
Check for fluid leakage after warming up A/T.