3) Install drain plug with gasket.

Tightening Torque (a): 23 Nm, (2.3 kg-m, 17.0 ft. lbs.) 

4) Remove exhaust pipe bracket and disconnect front propeller shaft from front differential (if equipped).
5) Remove oil pan bolts.
6) Remove oil pan.
7) Remove oil tubes.
8) Remove solenoid valve No. 1 (shift solenoid valve A and B) or solenoid valve No.2 (TCC solenoid valve).

OPERATION CHECK 

Whenever shift solenoid valves and TCC (lock-up) solenoid valve are removed from transmission, verify their valve function physically before they
are reinstalled.
1) Apply oiler to solenoid valve and give compression by hands and then check to be sure that transmission fluid from oiler does not come out of

holes in solenoid valve when battery voltage is not conducted.

2) Under the same conditions as above, conduct battery voltage and then make sure that fluid comes out with vigor.

NOTE: 
^

If fluid does not come out with vigor in above step 2 inspection, do not re-use that solenoid valve.

^

Figure at the left shows shift solenoid valve check. Check TCC solenoid valve also in the same way.

INSTALLATION 

Shift Solenoid, A/T|Specifications|Page 3823 > < Shift Solenoid, A/T|Specifications|Page 3821