T100 Extra Cab Pickup 4WD V6-3.4L (5VZ-FE) (1997)
b. Using a press, remove the hub sleeve No.2 assembly and 3rd gear assembly.
c. remove the needle roller bearing.
7. Remove shifting key and spring from hub sleeve No.2 assembly. Using a screwdriver, remove the three shifting keys and springs.
OUTPUT SHAFT COMPONENT PARTS INSPECTION
1. Inspect output shaft, as follows:
a. Using a micrometer, measure the output shaft flange thickness.
Minimum thickness: 4.70 mm (0.1850 inch).
If the thickness is less than the minimum, replace the output shaft.
b. Using a micrometer, measure the outer diameter of the output shaft journal.
Minimum diameter:
A 1st gear: 38.860 mm (1.5299 inch)
B 2nd gear: 46.860 mm (1.8499 inch).
C 3rd gear: 37.860 mm (1.4905 inch).
If the outer diameter is less than the minimum,replace the output shaft.
c. Using a dial indicator, check the shaft runout.
Maximum runout: 0.06 mm (0.0024 inch).
If the runout exceeds the maximum, replace the output shaft.
2. Inspect 1st and 2nd gears synchronizer ring, as follows:
a. Check for wear or damage.