HINT: Use the same procedure for the RH side as for the LH side.
9. INSTALL COMBINATION METER ASSEMBLY
10. INSTALL INSTRUMENT CLUSTER FINISH PANEL
11. INSTALL INSTRUMENT PANEL FINISH PANEL END RH
12. INSTALL INSTRUMENT PANEL FINISH PANEL END LH
13. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
Torque: 5.4 N*m (55 kgf*cm, 48 in.*lbf)
14. PERFORM CALIBRATION OF TORQUE SENSOR ZERO POINT.