Shift Solenoid: Testing and Inspection

Valve Body Solenoid Valves, Checking

This procedure is used to diagnose all Solenoid Valves in the valve body.

Special tools, testers and auxiliary items required

‹› Multimeter

‹› Wiring diagram

Requirements

‹› The Solenoid Valve fuses OK.

‹› The battery voltage must be at least 12.5 Volts.

‹› All electrical consumers must be switched off.

‹› The parking brake must be engaged.

‹› The selector lever must be in the "P" position.

‹› The Ground (GND) connections to transmission must be OK.

Test procedure

-

Perform a preliminary check to verify the customers complaint. Refer  to --> [ Preliminary Check ] See: Powertrain Management/Computers and
Control Systems/Testing and Inspection/Scan Tool Testing and Procedures/Preliminary Check.

Start diagnosis

Procedure

-

Disconnect the Solenoid Valve electrical harness  connector - 2 -.

-

Check the electrical harness connector for damage, corrosion, loose  or broken terminals.

Shift Solenoid, A/T|Testing and Inspection|Page 7976 > < Selector Lever Park Position Lock Switch|Page 7972