Shift Solenoid: Testing and Inspection

Solenoid Valves in Valve Body, Checking

This procedure is used to diagnose all Solenoid Valves in the valve body.

Special tools, testers and auxiliary items required

‹› Multimeter

‹› Wiring diagram

Requirements

‹› The Solenoid Valve fuses OK.

‹› The battery voltage must be at least 12.5 Volts.

‹› All electrical consumers must be switched off.

‹› The parking brake must be engaged.

‹› The elector lever must be in the "P" position.

‹› The Ground (GND) connections to transmission must be OK.

Procedure

-

Disconnect the Solenoid Valve electrical harness  connector - 2 -.

-

Check the electrical harness connector for damage, corrosion, loose  or broken terminals.

-

Repair any damage found to the electrical harness connector.

If the electrical harness connector is not OK:

-

Repair the malfunction.