C70 L5-2.4L Turbo VIN 63 B5244T7 (2003)
Spray base metallic paint first layer with normal flow.
Allow base metallic paint dry
Allow base metallic paint dry to a matt surface.
Note! Risk of patches if the drying time is too short.
Spray base metallic paint 2nd coat
Spray base metallic paint second coat with reduced flow (dry).
Increase spray stand. Base metallic coat should achieve 10-20 micron coat thickness after the second coat was applied. (If the second coat is sprayed
with greater flow the shade will be more strongly colored than if a thin coat was sprayed.)
Allow base metallic paint air dry
Allow the base metallic to air dry (airing) for approximately 15 minutes until a matt surface is obtained.
Note! If the base metallic paint is not completely dry when the varnish is applied there is a risk that paint will be patchy.
Spray varnish
Spray on varnish (two part) with good flow in two coats.
Wait 3-4 minutes between every coat.
Coat thickness 40-45 micron.
Allow the varnish to dry
Drying time/surface temperature:
12 hours/20°C (68°F)
Drying varnish with heat lamp or hot air gun