Installing high-pressure rail:

Installation of high-pressure rail is described separately from
removal.

Mount high-pressure rail (3), tightening screws hand-tight only in
the process.

Note:

It must still be possible for the high-pressure rail (3) to slide

on the cylinder head!

Connect contact plug (2).

Clip on cable holder (1).

Connect pressure lines (1), tightening nuts hand-tight only in the
process.

Important!

Connect pressure lines (1) without tension only.

In order to ensure that the pressure line is connected without
tension, it must be possible to screw on the nuts easily by
hand!

If a nut cannot be easily screwed on by hand, the
corresponding injector must be turned into the installation
position
.

Note:

Description of "Turning injector into installation position" in the
following two work steps.

Only if one injector has to be turned into installation position:

Release screw a few turns until holding-down element (1) is

slackened.

Turn injector (2) in direction of arrow until nuts on pressure

line can be easily screwed on by hand. 

To do so, engage wrench on hexagon head of injector if

necessary.

Tighten nuts on pressure line hand-tight.

Important!

RA  Removing and installing or replacing high-pressure rail (N43)

BMW AG - TIS

20.01.2013  10:37

Issue status (12/2007) Valid only until next DVD is issued

Copyright

Page  - 3 -

1 RA Removing And Installing Or Replacing High-pressure Rail (N43)|Page 694 > < 1 RA Removing And Installing Or Replacing High-pressure Rail (N43)|Page 692