7 Series E65 745d (M67TU) SAL
13 53 164
Replacing both pressure lines (between
pressure accumulators on left and right)
(M67TU)
Special tools required:
•
13 0 140
Necessary preliminary tasks:
•
Read out fault memories of DDE control units
•
Switch off ignition
•
Remove acoustic cover
•
Remove cover for injectors
•
Remove centre of assembly compartment bulkhead
•
Remove acoustic foam (rear side, intake air manifold)
•
Unlock plug on pressure regulator and disconnect
•
Unlock plug on differential pressure sensor and disconnect
•
Unlock plug on swirl flap actuator and disconnect
•
Release cable duct (on right from intake air manifold)
•
Release bracket (rear side, intake air manifold)
Unclip all lines and cables from holder
Important!
It is essential to adhere to conditions of absolute cleanliness
when working on the fuel system.
•
Do not allow any dirt particles or foreign bodies to get into the
system
•
Use only fluff-free cloths
•
Remove all traces of dirt before removing pipes or individual
components
•
Seal all fuel system openings with protective caps
RA Replacing both pressure lines (between pressure accumulators on left and right)
BMW AG - TIS
12.02.2013 14:30
Issue status (12/2007) Valid only until next DVD is issued
Copyright
Page - 1 -