Cylinder bank 5 to 8:
Remove oil line from VANOS adjustment unit.
Installation:
Replace sealing rings.
Attach oil line to VANOS adjustment unit.
Tightening Torque,
refer to Technical Data 11 36 9AZ.
Cylinder bank 5 to 8:
Fit special tool 11 7 130 to VANOS adjustment unit.
Connect up compressed air (2 to 8 bar).
Cylinder bank 5 to 8:
Disconnect plug connection for solenoid valves on cylinder
bank 5 to 8.
Connect special tool 12 6 050 in conjunction with special
tool 12 6 411 (from special tool kit 12 6 410) to solenoid
valves on cylinder bank 5 to 8. Connect special
tool 12 6 411 to correct terminals on car battery.
Alternately press toggle switch buttons 4 and 3 several times on
special tool 12 6 050.
Caution!
Do not damage the cylinder head.
If necessary, machine open-end wrench accordingly.