gmc Workshop Repair Guides

GMC Workshop Service and Repair Manuals

Power Steering Gear Replace|Page 5171 > < Power Steering Gear Replace|Page 5169
Page 9
background image

Fig. 19 Loading rack-piston nut

1.

Lubricate and install new ring back-up seal and Teflon piston ring on rack-piston nut, being careful ring and seal do not twist during installation.

2.

Insert worm into rack-piston nut to bearing shoulder.

3.

Align ball return guide holes with worm groove. Load balls into guide hole nearest the teflon piston ring while slowly rotating worm to left,
feeding balls through circuit, 

Fig. 19. If balls are installed properly, the worm should turn out of the rack-piston nut.

4.

Fill one-half of ball return guide with remaining balls. Place other guide over balls and plug each end with heavy grease to prevent balls from
falling out when installing guides into rack-piston nut.

5.

Insert guides into guide holes of rack-piston nut. Make sure black ball in guide is installed next to white ball in rack piston. Guides should fit
loosely.

Refitting Rack-Piston Balls

    Do not refit balls unless the steering is loose. If such is the case, a thrust adjustment and over-center adjustment should correct the problem if it lies in
the steering gear. If balls are pitted or rough, then select the proper ball size for proper adjustment.
    If the torque reading obtained above is too high or too low (on new balls only), disassemble and reassemble, using the next size smaller (or larger)
balls and recheck worm preload.
    A rack-piston nut with a ball size of 7 does not have a number stamped on the flat surface. For ball sizes other than 7, the ball size is stamped on the
flat surface of the rack-piston nut. Ball sizes are numbered from 6 to 11, with 6 being the smallest and 11 the largest. Ball sizes are graduated in
increments of .00008 inch from .28117 inch to .28157 inch.

Disassemble

Power Steering Gear Replace|Page 5171 > < Power Steering Gear Replace|Page 5169