mercedesbenz Workshop Repair Guides

Mercedes Benz Workshop Service and Repair Manuals

With Digital Tester (RIV Method)|Page 2074 > < With Digital Tester (RIV Method)|Page 2072
Page 1
background image

Injection Timing: Testing and Inspection
Flow Pressure Method

CHECKING INJECTION TIMING (BEGIN OF DELIVERY) (FLOW PRESSURE METHOD) 

Test value 

Start of delivery before TDC in compression stroke +24 ± 1°

Attention!  While conducting measurement, move injection pump control lever to full-load stop and disconnect vacuum hose from vacuum
control unit.

Tightening torques 

Pipe connection for delivery valves  .......................................................................................................................................  40-50 Nm (29-37 ft lb)
Injection lines  ................................................................................................................................................................................  25 Nm (18.5 ft lb)

Special tools 

Conventional tool 

Torque wrench 1/2" drive, 15-65 Nm

 
 

Testing 

1.  Clean injection pump at injection line cap nuts and pipe connections.

2.  Pull vacuum line from vacuum control unit.

3.  Unscrew injection line of No.1 cylinder.

With Digital Tester (RIV Method)|Page 2074 > < With Digital Tester (RIV Method)|Page 2072