Page 104
background image

6.1. Plug in connector on brake fluid reservoir -arrow- until it engages securely.

7. Screw on ground strap -1- on centre firewall.

7.1. Clip in wire harness on the firewall with the retaining clip -arrow A-.
7.2. Connect ground strap together with the twist lock to the threaded bolt on the centre firewall -arrow B- and secure with the fastening nut. -

Tightening torque: 9 Nm (6.5 ftlb.)

INFORMATION:
-

Select a place for the joint where there is enough space to join all the lines present.

-

Do not cut the lines too short in case they have to be laid in a different position if there is insufficient space in the area of the joint.

-

The electric lines are located in the plenum panel and are thus exposed to the highest demands.

-

The greatest care must be used in the individual work steps for stripping insulation from, crimping, and shrinking/insulating the electric lines.

-

The procedure for stripping insulation from, crimping, and shrinking/insulating the electric lines must be complied with and observed. The
procedures are described in detail in the Repair kit for Cayenne harnesses NR.155-2.

-

Crimping samples are to be prepared before beginning work.

8. Crimp the lines in area -a- (in cable duct above the pedals).

8.1. Cut off lines in different lengths (due to the shrink-fit connections).
8.2. Slide shrink-fit hoses onto the lines.
8.3. Strip 10 mm of insulation off the lines.
8.4. Crimp the lines using crimping sleeves and the manual crimping pliers from the repair kit for Cayenne wire harnesses NR.155-2.
8.5. Slide the shrink-fit hoses over the crimp connections and carefully shrink them using the hot-air blower with special nozzle (recommended

accessories for the repair kit for wire harnesses) so that they are watertight.

8.6. Wrap commercially available PVC tape all around the area of the connection points.

9. Secure the repaired area -b- to the main wire harness with tie-wraps.

10. Fit cover on cable duct (above the pedals) -arrow-.

Subsequent work

1. Install wiper motor.
2. Install linings in engine compartment.
3. Install heater/air-conditioning unit.
4. Install the carrier for the instrument panel.
5. Carry out work instructions after disconnecting the battery.

Procedures|Page 3540 > < Procedures|Page 3538