xB L4-2.4L (2AZ-FE) (2009)
Torque: 7.0 Nm (71 kgf-cm, 62 in-lbf)
(d) Connect the 2 connectors.
(e) Engage the 5 clamps.
(f) Connect the roof wire to the harness clamp.
(g) Connect the roof wire connector.
(h) Engage the 4 clamps.
(i) Connect the antenna cord connector.
12. INSTALL UPPER INSTRUMENT PANEL SUB-ASSEMBLY See: Dashboard / Instrument Panel/Service and Repair/Upper Instrument
Panel/Installation
13. INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY See: Dashboard / Instrument Panel/Service and Repair/Upper Instrument
Panel/Installation
14. INSTALL COMBINATION METER ASSEMBLY See: Instrument Panel, Gauges and Warning Indicators/Instrument Cluster / Carrier/Service
and Repair/Combination Meter/Installation
15. INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY See: Dashboard / Instrument Panel/Service and Repair/Upper Instrument
Panel/Installation
16. INSTALL INSTRUMENT CLUSTER FINISH LOWER PANEL See: Dashboard / Instrument Panel/Service and Repair/Upper Instrument
Panel/Installation
17. INSTALL INSTRUMENT CLUSTER FINISH CENTER PANEL SUB-ASSEMBLY See: Dashboard / Instrument Panel/Service and
Repair/Upper Instrument Panel/Installation
18. INSTALL MAP LIGHT ASSEMBLY