Up!
|
Note
t | The tank flap unit may be engaged in side panel with 1 or 2 locking hooks. |
t | Accordingly, there are 1 or 2 markings on the tank flap unit. |
t | In the illustrations the version with 1 locking hook is shown. |
Carry out following work: |
– | Screw off tank cover. |
– | Insert a screwdriver -2- into the marked opening -3-. |
– | Release locking hook -arrow b-. |
– | Swing tank flap unit -1- out of side panel -arrow c-. |
– | Guide water drainage hose -4- together with tank flap unit out of side panel. |
|
Carry out following work: |
– | Insert water drainage hose -3- through opening in tank flap unit -1- and then pull it through as far as it will go. |
– | Push water drainage hose -3- into side panel. |
– | Swing tank flap unit -1- into side panel and pull sleeve over filler neck. |
– | Then insert tank flap unit into side panel completely. Make sure that locking hook -2- engages correctly in side panel. |
l | Perform functional check of release components. |