Supplementary work for basic throttle setting
(S62)

This work is carried out:

on engines with adjustable pull rods at both cylinder banks

if the throttle opening of 24.2 mm 

±

 0.5 mm cannot be

achieved when the full-load adaptation stop is set

The non-adjustable pull rod (1) of cylinder bank 1-4 is replaced
by an adjustable pull rod (2) (versions as on cylinder bank 5-8). 

Clip in adjustable pull rod (2) of cylinder bank 1-4 on throttle side
only.

Clip in adjustable pull rod of cylinder bank 5-8 on throttle and
servomotor sides.

Turn back stop screw (1) a few turns. 

This ensures that the stop screw does not influence the
servomotor-side stop.

Activate servomotor at specified value 100 % and check
whether measurement (A) = 24.2 mm 

±

 0.5 mm is achieved.

RA  Supplementary work for basic throttle setting (S62)

BMW AG - TIS

21.02.2013  16:34

Issue status (12/2007) Valid only until next DVD is issued

Copyright

Page  - 1 -

3 RA Supplementary Work For Basic Throttle Setting (S62)|Page 1354 > < 2 RA Replacing Complete Injection Pipe (S62)|Page 1352