kit.

If replacement of only the thrust bearing (Figure 2) (677) 4T60 or (676) 3T40 is necessary, use Steps 1 through 3. After Steps 1 through 3 are completed,
move the pinion gears to provide clearance to replace the thrust bearing, then complete Steps 6 through 7 of the assembly procedure.

Assembly

1.

After cleaning the pinion gear, apply Transjel J36850 (assembly lubricant or petroleum jelly) to the inside of the gear. (Do not use any grease or
axle grease.)

2.

Install square cut washer (809) onto the pinion gear shaft (804). Insert the shaft and washer into the gear so the washer is flush with gear and shaft
is 3/4 inside gear.

Important:
Square cut washer is to be assembled between the two rows of needle bearings.

3.

Install needle bearings (805) (one at a time) into the gear - 44 per pinion (22/row) for 3.06 and 3.33 ratios - 36 per pinion (18/row) for 2.84 ratio.
Occasionally, twist the pinion shaft so the needle bearings will line up and allow for all needle bearings to be installed. (Figure 5)

4.

Install 2 washers (807) into the final drive assembly. (Figure 6)

5.

Install the remaining 2 washers (807) (on top of the pinion gear). (Figure 6)

6.

Insert the pinion gear and washers (in same position it was removed) into the final drive. Check the chalk or crayon mark.

Important:
Make sure the pinion gear is installed the same way that it was removed. If the gear is installed upside down, it may cause a noise because of the change
in set - wear pattern.

7.

Install the pinion gear shaft (804) (without dislodging the needle bearings) and install the spiral snap ring. (Figure 6)

Important:
Make sure there are no extra needle bearings left after replacing the washers. There must be no spaces between needle bearings. Check for pinion end
play.

Do not install more than the required amount of washers, four (4) per each pinion (2 on each side of pinion), into the final drive.

LABOR TIME INFORMATION

Add .4 hours to Labor Operation K7620 whenever this service procedure is performed.

SERVICE PARTS INFORMATION

Whenever ordering replacement parts for the final drive assembly refer to the following part numbers:

Package Description

Part Numbers

Package:

Pinion, thrust washers for 2.84 ratio

8637994 

final drive - 16 steel washers (807)

Package:

Pinion, thrust washers for 3.06 and 3.33

8637995 

ratio final drive - 16 steel washers (807)

Bearing, differential sun gear

8646254

Parts are currently available from GMSPO.

SERVICE MANUAL REFERENCE

Whenever service and/or replacement to the final drive assembly is necessary, refer to the Unit Repair section of your Service Manual.