IS 250C V6-2.5L (4GR-FSE) (2011)
(a) Measure the resistance according to the value(s) in the table below.
Text in Illustration
Standard Resistance:
(b) Connect a positive (+) lead to the terminal of the solenoid connector, and a negative (-) lead to the solenoid body.
OK:
The solenoid makes an operating sound.
If the resistance is not within the specified range, replace the shift solenoid valve S4.
6. INSPECT SHIFT SOLENOID VALVE SL2
(a) Measure the resistance according to the value(s) in the table below.
Text in Illustration
Standard Resistance:
(b) Connect a positive (+) lead with a 21 W bulb to terminal 2 and a negative (-) lead to terminal 1 of the solenoid valve connector, then check the
operation of the valve.
OK:
The solenoid makes an operating sound.
If the resistance is not within the specified range, replace the shift solenoid valve SL2.
7. INSPECT SHIFT SOLENOID VALVE SR
(a) Measure the resistance according to the value(s) in the table below.