| Position the reservoir -1- on the engine pump aggregate -2-. |
–
| Position the reservoir in such a way that the connection fitting for the return-flow line -arrow A- is located vertically above the screw connection for the pressure line -arrow B-. |
–
| Pull the reservoir -1- up to the stop onto the engine pump aggregate -2-. |
–
| For this step knock with a rubber hammer evenly all around on the reservoir -1-, but on no account on the filler tube. |
–
| Ensure that the reservoir does not tilt. |
–
| Attach reservoir with a new clamp at engine pump aggregate. |
–
| Tighten screws of the clamp to specified tightening torque. |
–
| Close connection fitting for the return-flow line at reservoir. |
–
| Fill reservoir up to approx. 1/4 with hydraulic oil and check for tightness at joint of reservoir/engine pump aggregate. |
–
| In case of leaks eliminate the fault. |
For reasons of guarantee, mark the replacement of the reservoir. |
|
|
|