A4 Quattro Cabriolet V6-3.2L (BKH) (2007)
Note:
^
Never install assembly appliance onto balance plates.
-
Remove securing bolts -arrows- for the center bearing.
-
Screw in bolt -3- M10 x 100 into rear final drive.
-
To loosen bolts -1- of the rear and front drive shaft, counterhold with an assembly lever -2-.
-
Remove securing bolts at the front constant velocity joint, detach the drive shaft and support it using engine/transmission jack VAG 1383 A.
-
Remove securing bolts at rear constant velocity joint and detach drive shaft.
Note:
^
Only transport and store drive shaft when extended.
Installing
Installation is carried out in reverse order. Note the following:
Note:
^
To avoid imbalance, the flanges of the drive shaft -arrow A- and of the rear final drive arrow B- must be installed so that the factory color
markings or the markings made subsequently are in line.
^
If a new drive shaft is installed and if the factory color marking on the flange of the rear final drive is no longer visible, the radial run-out on the
drive shaft flange must be measured and the color marking on the drive shaft placed in line with the new marking on the flange.
^
Replace gaskets on flange shafts (detach protective foil and stick gasket onto flange shaft).
^
Remove the old and dry high-temperature grease from the constant velocity joints and the flanges for the drive shaft. Replace with the exact same