01 Engine02 Gearbox and clutch03 Transmission and driveshafts04 Suspension05 Steering06 Brakes07 Body - front section08 Body - rear section09 Body - side structure10 Front doors and trim11 Rear doors and trim12 Body - roof and headlining13 Body shell14 Lighting and signalling15 Wipers and washers16 Fascia and interior panels17 Front seats18 Rear seats19 Interior trim20 Electrical - general21 Starting and charging22 Wiring harnesses23 Instruments and warning lamps24 Locking, alarm and airbags25 Electrical - driver assistance systems26 Heating, air conditioning and audio
Citroën C3 (A51) Factory Workshop Manual (2016-2024)09 · Body - side structure
09 · Body & interior

Replacement: Outer sill (floor)

Make
Citroën
Model
C3 (A51) Factory Workshop Manual
Year
2016–2024
Section
Understructure › Replacement: Outer sill (floor)
Body - side structureReplacement: Outer sill (floor)

Replacement: Outer sill (floor)

Citroën C3 (A51) · Replacement · Ref. C4CH017MP0

Applies to: 5 door saloon or Firm 5 door saloon

ESSENTIAL: Observe the safety and cleanliness recommendations.

ESSENTIAL: Observe the precautions to be taken for the pre-tensioning components.

ESSENTIAL: For any paint retouching operation on a vehicle that has the STOP and START system requiring a paint booth, it is necessary to remove the central voltage retention device assembly (DMTC) if the temperature exceeds 80°C.

CAUTION: All of the stripped surfaces must be protected by means of the approved electrolytic rezincing process.

CAUTION: The number of spot welds necessary for the assembly of a new part must be identical to the number of spot welds fixing the original part.

1. Information

N.B.: Use the products recommended by the manufacturer.

Types of weld bead by electric arc procedure on this component.

MAG welding with steel rod and used with active gas.

Designations of the high strength steels used in this document:

  • High strength: High strength steel
  • THLE: Very high strength steel
  • UHLE: ultra high strength steel

2. Tooling

toolReferenceDesignation
Figure e5ah002t
[1366-ZZ]Toolkit for testing electric spot welds
Figure e5ah003t
[1366-B]Samples for testing electric spot welds
Figure e5ah005t
Electric knife kit FEIN
-"C1" electric knife
-"C2" FEIN offset hub saw blade
-"C3" Blade no. 103
Figure e5ah004t
Swan’s neck drill for cutting out electric spot welds

3. Additional operations

Deactivating the pyrotechnic systems.

Disconnect the battery.

CAUTION: Remove or protect the components that are in the repair area and that can be damaged by heat or dust.

Remove:

  • The front door
  • The rear door
  • The front wing
  • The interior trims

Release the wiring harnesses.

4. Location: Replacement part

Figure c4ch0o1d
ReferenceDesignation
(1)Outer sill   (floor)

5. Identification of the replacement part

5.1. Composition: Outer sill   (floor)

Figure c4ch0o2d
ReferenceDesignationThicknessNature/classification
(1)Outer sill   (floor)0,67 mmMild steel

5.2. Identification of the parts adjacent to the replacement part

Figure c4ch0o3d
ReferenceDesignationThicknessNature/classification
(2)Front pillar strengthener1,17 mmHigh strength
(3)Front wing inner panel1,17 mmHigh strength
(4)Centre pillar inner panel0,87 mmMild steel
(5)Rear quarter panel inner panel0,67 mmMild steel
(6)Inner sill   (rear section)1,47 mmHigh strength
(7)Sill strengthener0,97 mmTHLE
(8)Centre pillar lower reinforcement1,6 mmHigh strength
(9)Centre pillar upper strengthener1,6 mmUHLE
(10)Inner sill   (front section)1,95 mmHigh strength

6. Preparation: Replacement parts

Figure c4ch0o4d

CAUTION: When cleaning the mating edges, use scouring wheels only to avoid damaging the anticorrosion protection.

Mark out then cut (at "a", "b", "c") in the cutting zones "A", "B", "C".

N.B.: The cutting lines "a", "b", "c" are shown as an indication only. The dimensions can change depending on the different sill replacement examples.

Prepare the mating edges and protect them using a weldable primer (index "C7").

N.B.: Apply the weld-through primer on the internal faces of the panels to be welded.

7. Cutting of the part on the body

Figure c4ch0o5d

Unclip: The plugs (11).

Figure c4ch0o6d

Mark out then cut (at "d", "e", "f") in the cutting zones "D", "E", "F".

N.B.: The cutting lines "d", "e", "f" are shown as an indication only. The dimensions can change depending on the different sill replacement examples.

Figure c4ch0o7d

Cut out the spot welds.

Figure c4ch0o8d

Cut out the spot weld.

Figure c4ch0o9d

Detach the external side member   (floor)   At the inflating inserts (12), (13), (14), (15); Using a hot air gun.

Remove the exterior longeron   (floor).

8. Cleaning and preparation of the body

Figure c4ch0oad

Prepare the mating edges and protect them using a weldable primer (index "C7").

N.B.: Apply the weld-through primer on the internal faces of the panels to be welded.

Figure c4ch0obd

Prepare the mating edges and protect them using a weldable primer (index "C7").

N.B.: Apply the weld-through primer on the internal faces of the panels to be welded.

Figure c4ch0ocd

Seal the expanding inserts (12), (13), (14), (15).

Apply a gap-filling adhesive A1 to the rear wheel arch   (at "g").

9. Adjustment

Position:

  • The outer sill   (floor)
  • The components for adjusting

Check: The fits and clearances.

Holds the part in position.

10. Welding

Figure c4ch0odd

Weld with MAG beads   (at "h", "j", "k").

Grind the MAG weld beads.

Figure c4ch0oed

Weld with electric spot welds.

Figure c4ch0ofd

Weld with electric spot welds.

11. Sealing protection

Figure c4ch0ogd

Apply a phosphate-print layer to the zones laid bare.

Apply index "A1" sealing mastic at.

Figure c4ch0ohd

Apply a phosphate-print layer to the zones laid bare.

Apply index "C4" underseal protection.

CAUTION: Do not block the drain holds with the stone chip protection   (at "l").

Figure c4ch0oid

Inject index "C6" polyurethane foam at the insert (15).

Figure c4ch0ojd

Apply a sealing mastic index A1 around the plug (11).

Reclip the plug (11).

Painting, then spraying of the index "C5" product into the hollow sections in the repair zone.

12. Additional operations

Refit the electrical harnesses and the components removed.

13. Reinitialisation

Put the pyrotechnic systems into service.

CAUTION: Perform the operations to be carried out following reconnection of the battery.

Reconnect the battery.

Parts & tools for this job For 2016 Citroën C3