Workshop Manuals Factory service & repair Citroën
01 Engine02 Gearbox and clutch03 Transmission and driveshafts04 Suspension05 Steering06 Brakes07 Body - front section08 Body - rear section09 Body - side structure10 Front doors and trim11 Rear doors and trim12 Body - roof and headlining13 Body shell14 Lighting and signalling15 Wipers and washers16 Fascia and interior panels17 Front seats18 Rear seats19 Electrical - general20 Starting and charging21 Wiring harnesses22 Locking, alarm and airbags23 Electrical - driver assistance systems24 Heating, air conditioning and audio
Citroën C-Crosser Factory Workshop Manual (2007-2012)01 · Engine
01 · Engine

Checking: Setting the valve timing

Make
Citroën
Model
C-Crosser Factory Workshop Manual
Year
2007–2012
Section
Timing gear › Checking: Setting the valve timing
EngineChecking: Setting the valve timing

Checking: Setting the valve timing

Citroën C-Crosser · Checks · Ref. B1ED0123P0

Applies to: 2.0 i mmc EURO4 or 2.4 i mmc EURO5

ESSENTIAL: Observe the safety and cleanliness recommendations.

Disconnect the battery.

1. Removing

Figure b1bm0d4d

Remove:

  • The stabiliser bar (2)   (according to equipment)
  • The engine cover (6)
  • The ignition coils cover (5)

Disconnect and remove: The ignition coils (1).

Uncouple the oil vapour resuction pipes (3), (4).

Figure b1ed0a5d

Remove - Release: The coolant reservoir (11).

Remove:

  • The (7) bolt (Coolant piping)
  • The bolt (8) (Power steering pipe) (according to equipment)
  • The power steering union (9)   (according to equipment)

Uncouple: The power steering pipe (10)   (according to equipment).

CAUTION: Close: The power steering pipes; Using plugs   (according to equipment).

Figure b1dm067d

Remove:

  • The bolts of the cylinder head cover (12) (In the order shown)
  • The cylinder head cover

2. Checking the valve timing

Figure b1em05ad

Turn the engine clockwise using the ancillary drive pulley bolt until the marks on the two camshafts are aligned   (at "a").

N.B.: The marks (at "a") must be aligned in relation to the cylinder head cover joint face.

Raise the vehicle and support on axle stands, wheels free.

Remove:

  • The protective panel under the engine   (according to equipment)
  • The splash shield (Front right-hand wheel)
Figure b1em05bd

Check that cylinder n°1 (timing side) is at top dead centre (At the end of compression).

Check the alignment of the mark on the ancillary drive pulley at "b" in relation to the mark at "c" on the timing cover.

N.B.: If the marks are not aligned, restart the operations for refitting the timing chain.

3. Refitting

Figure b1ed0a7d

Apply a bead of sealing paste approximately 4 mm in diameter to the joint face of the cylinder head cover   (at "d").

Refit:

  • The splash shield (Front right-hand wheel)
  • The protective panel under the engine   (according to equipment)
  • The cylinder head cover
  • The bolts of the cylinder head cover (12) (In the order shown)

Couple up: The power steering pipe (10)   (according to equipment).

Refit:

  • The power steering union (9)
  • The bolt (8) (Power steering pipe) (according to equipment)
  • The bolt (7) (Coolant piping)
  • The coolant reservoir (11)

Couple up the oil vapour resuction pipes (3), (4).

Refit and connect the ignition coils (1).

Refit:

  • The ignition coils cover (5)
  • The engine cover (6)
  • The stabiliser bar (2)   (according to equipment)

CAUTION: Perform the operations to be carried out following reconnection of the battery.

Reconnect the battery.