4. NOTE: Aisin AW21 shown, 6F35 similar.

NOTE: When installing the selector lever cable, make sure that the selector lever cable locking tabs are locked in place and the selector lever
cable end is snapped onto the ball stud. Press the selector lever cable into the bracket and listen for the selector lever cable to click in place. Pull
back on the selector lever cable to make sure that it is locked into the selector lever cable bracket. Also make sure that the selector lever cable end
is correctly installed onto the ball stud. Pull back on the selector lever cable end to make sure that the selector lever cable end is correctly installed.

Install the selector lever cable in the bracket. Be sure the tabs are locked in place.

5. NOTE: Aisin AW21 shown, 6F35 similar.

Connect the selector lever cable end on the manual control lever.

6. Install the battery and battery tray. For additional information, refer to Battery.

7. Install the RCM. For additional information, refer to Restraint Systems.

8. Install the heater core and evaporator core housing.

9. Adjust the selector lever cable. For additional information, refer to Selector Lever Cable Adjustment - Aisin AW21  See: Adjustments/Selector

Lever Cable Adjustment - Aisin AW21 or Selector Lever Cable Adjustment - 6F35  See: Adjustments/Selector Lever Cable Adjustment - 6F35.